First Vice President Eshaq Jahangiri, Iranian Minister of Petroleum Bijan Zangeneh and NIGC Managing Director Hamid Reza Araghi are scheduled to attend a ceremony that will be held to launch the projects.
Each of the facilities are equipped with 4 25-megawatt turbo-compressors which were installed within a period of 30 months with IRR11,600b of investment.
He also said each of the turbo-compressors were constructed by Iranian manufacturers, too.